Mid-2030s
ReFirm – Studsvik
Studsvik, Nyköping, Södermanland
Status
Government Application
Zoning Permit
Environmental Permit
License
ReFirm – Studsvik
Details
Focusing on SMR campuses across the Nordic region, with initial plans concentrated in southern Sweden to address high regional electricity demand and decarbonize industrial sectors.
Company Background: Kärnfull Next has been developing SMR sites in the Nordics since 2019 and was acquired by nuclear technology firm Studsvik AB in early 2026 to accelerate "ready-to-build" projects.
Technology and Capacity: Plans to deploy up to 1,400 MW of new nuclear power capacity using factory-built SMRs, offering flexible grid electricity, district heating, and co-location with data centers.
Financing and Timeline: Submitted an application for Swedish state support in June 2026. Aims to have operational, cost-optimized SMR units up and running in the early 2030s.
Project Status
Government Application
Zoning Permit
Environmental Permit
License
Proposed Site
Location:
Studsvik, Nyköping, Södermanland
Municipality:
nyköping
Technology
Supplier:
Proposed Reactors:
4
Total Capacity (MWe):
1200
ReFirm – Studsvik
Location
Following its acquisition of SMR developer Kärnfull Next, Studsvik AB is developing a site for two to four light-water SMRs at its established nuclear research brownfield site.
Location: The coastal Studsvik industrial and nuclear research area outside Nyköping in Södermanland County.
Zoning Permit Area: The total planning area encompasses roughly 230 hectares (building upon an existing 150-hectare zoned industrial zone), with the final reactor facility footprint estimated to occupy 30 to 50 hectares.
Reviewing Municipality: Nyköping Municipality (Nyköpings kommun), alongside facility plan preparation by the Södermanland County Administrative Board.
Hover for more detail
Zoning Details
Land use:
Industrial, development and operation of nuclear power plant and related functions
ReFirm – Studsvik
Latest News
ReFirm – Studsvik
Documentation
Here you can find documents that are relevant to the project. Only publicly available documents are displayed. For more information please visit the official website of the project owner.
Governmental & Municipal
Zoning & Construction
Environmental
License

Mid-2030s
ReFirm – Studsvik
Studsvik, Nyköping, Södermanland
Status
Government Application
Zoning Permit
Environmental Permit
License
ReFirm – Studsvik
Details
Focusing on SMR campuses across the Nordic region, with initial plans concentrated in southern Sweden to address high regional electricity demand and decarbonize industrial sectors.
Company Background: Kärnfull Next has been developing SMR sites in the Nordics since 2019 and was acquired by nuclear technology firm Studsvik AB in early 2026 to accelerate "ready-to-build" projects.
Technology and Capacity: Plans to deploy up to 1,400 MW of new nuclear power capacity using factory-built SMRs, offering flexible grid electricity, district heating, and co-location with data centers.
Financing and Timeline: Submitted an application for Swedish state support in June 2026. Aims to have operational, cost-optimized SMR units up and running in the early 2030s.
Project Status
Government Application
Zoning Permit
Environmental Permit
License
Proposed Site
Location:
Studsvik, Nyköping, Södermanland
Municipality:
nyköping
Technology
Supplier:
Proposed Reactors:
4
Total Capacity (MWe):
1200
ReFirm – Studsvik
Location
Following its acquisition of SMR developer Kärnfull Next, Studsvik AB is developing a site for two to four light-water SMRs at its established nuclear research brownfield site.
Location: The coastal Studsvik industrial and nuclear research area outside Nyköping in Södermanland County.
Zoning Permit Area: The total planning area encompasses roughly 230 hectares (building upon an existing 150-hectare zoned industrial zone), with the final reactor facility footprint estimated to occupy 30 to 50 hectares.
Reviewing Municipality: Nyköping Municipality (Nyköpings kommun), alongside facility plan preparation by the Södermanland County Administrative Board.
Hover for more detail
Zoning Details
Land use:
Industrial, development and operation of nuclear power plant and related functions
ReFirm – Studsvik
Latest News
ReFirm – Studsvik
Documentation
Here you can find documents that are relevant to the project. Only publicly available documents are displayed. For more information please visit the official website of the project owner.
Governmental & Municipal
Zoning & Construction
Environmental
License

Mid-2030s
ReFirm – Studsvik
Studsvik, Nyköping, Södermanland
Status
Government Application
Zoning Permit
Environmental Permit
License
ReFirm – Studsvik
Details
Focusing on SMR campuses across the Nordic region, with initial plans concentrated in southern Sweden to address high regional electricity demand and decarbonize industrial sectors.
Company Background: Kärnfull Next has been developing SMR sites in the Nordics since 2019 and was acquired by nuclear technology firm Studsvik AB in early 2026 to accelerate "ready-to-build" projects.
Technology and Capacity: Plans to deploy up to 1,400 MW of new nuclear power capacity using factory-built SMRs, offering flexible grid electricity, district heating, and co-location with data centers.
Financing and Timeline: Submitted an application for Swedish state support in June 2026. Aims to have operational, cost-optimized SMR units up and running in the early 2030s.
Project Status
Government Application
Zoning Permit
Environmental Permit
License
Proposed Site
Location:
Studsvik, Nyköping, Södermanland
Municipality:
nyköping
Technology
Supplier:
Proposed Reactors:
4
Total Capacity (MWe):
1200
ReFirm – Studsvik
Location
Following its acquisition of SMR developer Kärnfull Next, Studsvik AB is developing a site for two to four light-water SMRs at its established nuclear research brownfield site.
Location: The coastal Studsvik industrial and nuclear research area outside Nyköping in Södermanland County.
Zoning Permit Area: The total planning area encompasses roughly 230 hectares (building upon an existing 150-hectare zoned industrial zone), with the final reactor facility footprint estimated to occupy 30 to 50 hectares.
Reviewing Municipality: Nyköping Municipality (Nyköpings kommun), alongside facility plan preparation by the Södermanland County Administrative Board.
Hover for more detail
Zoning Details
Land use:
Industrial, development and operation of nuclear power plant and related functions
ReFirm – Studsvik
Latest News
ReFirm – Studsvik
Documentation
Here you can find documents that are relevant to the project. Only publicly available documents are displayed. For more information please visit the official website of the project owner.